Fortune Minerals announces positive updated Micon Feasibility Study & updated reserves for the NICO project


Save Story

Estimated read time: 21-22 minutes

This archived news story is available only for your personal, non-commercial use. Information in the story may be outdated or superseded by additional information. Reading or replaying the story in its archived form does not constitute a republication of the story.

[STK] OTC-QX:FTMDF OtherOTC:FTMDF Toronto:FT

[IN] MNG

[SU]

TO BUSINESS EDITORS:

Fortune Minerals announces positive updated Micon Feasibility Study &

updated reserves for the NICO project

Improved economics at lower commodity price assumptions to advance

project financing

Issued Capital: 150,526,976

LONDON, ON, April 2, 2014/CNW/ - Fortune Minerals Limited (TSX: FT)

(OTCQX: FTMDF) ("Fortune" or the "Company") (www.fortuneminerals.com)

is pleased to announce the results of an updated Feasibility Study

report by Micon International Limited ("Micon") for Fortune's 100%

owned NICO gold-cobalt-bismuth-copper project. NICO is a planned

vertically integrated project consisting of an open pit and

underground mine and mill near Yellowknife in the Northwest

Territories ("NT") and a hydrometallurgical refinery near Saskatoon -

the Saskatchewan Metals Processing Plant ("SMPP"), where Fortune will

process concentrates from the mine to high value metal products. Both

sites have already received the environmental assessment ("EA")

approvals in their respective jurisdictions and are now in the final

permitting phase.

This updated Feasibility Study was prepared by Micon in order to

document a number of improvements that have been made to the NICO

project over the past year and to provide a comprehensive document to

support negotiations currently underway for project financing with

potential strategic partners and their banks. It updates the economics

for the project from the 2012 front-end engineering and design

("FEED") study by Jacobs Minerals Canada Inc. ("Jacobs") and other

engineering companies, which is summarized in a technical report by

P&E Mining Consultants Inc. ("P&E") and other engineering companies

filed on the SEDAR website (www.sedar.com) (see Fortune news release,

dated July 2, 2012). Areas where improvements have been made include:

the inclusion of additional gold-rich reserves to be accessed from

underground outside of the open pit design, use of grid power at the

minesite rather than expensive diesel power, updated capital and

operating costs to reflect current prices and updated labour and

indirect costs, and changes in product mix and markets with the

inclusion of additional bismuth premium products to be pursued to

reflect the SMPP's strategic advantage as a North American based

producer of specialty metals and chemicals. The Qualified Persons

responsible for the Micon Feasibility Study for the purposes of

National Instrument 43-101 are: Chris Lattanzi, P.Eng., Richard

Gowans, P.Eng. Harry Burgess, P.Eng. and Terrence Hennessey, P.Geo.

The information used in the Micon Feasibility Study incorporates

updated capital and operating costs and site designs by Procon Mining

& Tunnelling Inc. ("Procon") and Hatch Engineering, additional

underground reserves and mining designs by Procon and a financial

model, execution plan and marketing information supplied by Fortune.

The Micon study also relies on information previously reported in the

2012 FEED study, which includes: the minesite, concentrator and SMPP

process plant designs by Jacobs with minor updates by SGS and Procon;

the mine plan and schedule, mineral resources, and mineral reserves by

P&E - except for additional underground reserves primarily outside of

the open pit design that were developed and confirmed by Procon;

metallurgical test work by SGS Lakefield Research Limited ("SGS");

waste rock disposal and tailings disposal and design, effluent

treatment design and environmental and permitting work by Golder

Associates Limited; mine access road design by EBA Engineering Limited

("EBA"); and site infrastructure by Jacobs, International Quest

Engineering Ltd., and EBA, with minor amendments by Procon and

Fortune. A technical report for the Micon Feasibility Study prepared

in accordance with National Instrument 43-101 will also be filed on

SEDAR within 45 days of this news release.

Highlights of the Micon Feasibility Study:

-- Increase in Mineral Reserves to 33.1 million tonnes;

-- Increase in Gold contained in the deposit to more than 1.1 million

ounces;

-- Levered Base Case pre-tax Internal Rate of Return ("IRR") of 15.6%

(after-tax 15.1 using lower commodity prices than the FEED study;

-- Levered Base Case pre-tax 7% discounted Net Present Value ("NPV")

of C$254 million (C$224 million after tax);

-- Cycle metal price sensitivity analysis indicating potential for

levered 7% discounted pre-tax NPV of C$543 million and IRR of 23.6%

(C$505 million NPV and 23.2% IRR after-tax);

-- Pre-production capital of C$589 million, including indirects and

EPC costs;

-- Low C1 cash operating cost for metals: US$ 673.54/equivalent gold

ounce; US$ 9.50/equivalent cobalt pound; US$ (702.12)/ounce of gold

net of by-product credits; US$ (5.19)/pound of cobalt net of

by-product credits; US$ (10.18)/pound of bismuth net of by-product

credits;

-- 20-year life of mine ("LOM") metal production of: 814,000 troy

ounces of gold as doré; 70 million pounds of cobalt in cobalt sulphate

containing 20.9% cobalt; 74 million pounds of bismuth as 99.995% ingot

and needles, and bismuth oxide containing 89.7% bismuth; 11.2 million

pounds of copper in a copper cement precipitate.

Robin Goad, Fortune's President and Chief Executive Officer commented,

"As we complete the final stages of permitting and project financing

for NICO, Fortune is well-positioned to be a reliable North American

source of supply of cobalt and bismuth and a highly liquid gold

co-product. Our proposed Saskatchewan refinery will stand out as a

North American facility dedicated to the production of cobalt

chemicals needed to manufacture rechargeable batteries used in

portable electronic devices and electric vehicles, the latter

currently driving transformational growth in the market for cobalt.

NICO is also the world's largest single known deposit of bismuth,

which is also experiencing increasing demand as a non-toxic,

environmentally safe replacement for lead due to bans and restricted

use of lead as a result of legislation and growing environmental

awareness by manufacturers. A recovering world economy, growth in the

use of our specialty metals, and supply concerns from traditional

producers will collectively make Fortune an attractive NAFTA supplier

of cobalt and bismuth."

Mike Romaniuk, Fortune's Vice President and Chief Operating Officer

commented, "This update has produced a document with a project

execution that we believe is achievable and with a schedule and costs

that reflect the current market. The increased capital cost better

reflects the labor and indirect costs expected in the locations for

the mine and processing facilities. The additional efforts to realize

opportunities in mining outside of the pit shell, grid power for the

mine, and greater clarity on final product mix and markets has

justified an update to the previously released information."

Location and Access for the NICO Mine and SMPP:

The NICO deposit and proposed mine and mill are located in the NT, 160

km northwest of the City of Yellowknife and 50 km northeast of the

Tlicho aboriginal community of Whati. An access road will be

constructed to join with a new all-weather road proposed from Whati to

the highway at Behchoko, 85 km south of NICO. The road will enable the

Company to truck bulk concentrate from the mill to Hay River, NT for

trans-loading onto rail and delivery to the SMPP. Fortune owns 194

hectares of lands straddling the CN Rail line near Langham,

Saskatchewan, 26 km northwest of Saskatoon and about 2 km north of the

Yellowhead highway.

Updated Mineral Reserves:

NICO is an Iron Oxide Copper-Gold ("IOCG") class deposit, also

commonly referred to as Olympic Dam-type after the "Super Giant"

deposit in South Australia that defines this class. Ore is hosted in

three, 40-50 degree dipping stratabound lenses of brecciated ironstone

up to 1.3km in length, 550 metres in width and with individual lenses

up to 70 metres in true thickness. The recoverable metals are

associated with the approximate 5% sulphide fraction consisting

primarily of cobaltian arsenopyrite, cobaltite, bismuthinite,

chalcopyrite, pyrite and pyrrhotite, as well as native gold and

bismuth.

The mineral resources and mineral reserves for the NICO deposit were

prepared by P&E for the 2012 FEED study based on a geological block

model determined from data from 327 drill holes, plus surface

trenches, and operating cost net smelter return ("NSR") cut-off

values. Mineral reserves were determined from the mineral resources

based on operating costs. An additional 89,000 tonnes of underground

mineral reserves were identified and confirmed by Procon and Fortune

outside of the open pit design prepared by P&E. The updated combined

Mineral Reserves are shown in the table below.

Underground Mineral Reserves

Classification Tonnes (Thousand) Au (g/t) Co ( Bi (%) Cu (%)

Proven 282 4.93 0.14 0.27 0.03

Probable 295 5.00 0.07 0.07 0.01

Total 577 4.96 0.10 0.17 0.02

Open Pit Mineral Reserves

Classification Tonnes (Thousand) Au (g/t) Co ( Bi (%) Cu (%)

Proven 20,453 0.92 0.11 0.15 0.04

Probable 12,047 1.03 0.11 0.13 0.04

Total 32,500 0.96 0.11 0.14 0.04

Underground and Open Pit Combined Mineral Reserves

Classification Tonnes (thousand) Au (g/t) Co ( Bi (%) Cu (%)

Proven 20,735 0.97 0.11 0.15 0.04

Probable 12,342 1.13 0.11 0.13 0.04

Total 33,077 1.03 0.11 0.14 0.04

Metal Contained1 1,100 Moz 82.3 Mlb 102.1 Mlb 27.2 Mlb

Sums of the combined reserves may not exactly equal sums of the

underground and open pit reserves due to rounding error.

The geological block model consists of the aggregate of five metre

cubed individual blocks with grades assigned by the interpolation of

composited assay data using Indicator Kriging. The resource estimate

was also verified using Nearest Neighbor interpolation, which

generated similar results. The composite database was subjected to

geostatistical analysis to limit the influence of grades that were

considered statistically anomalous, and established grade caps of 24

grams/tonne ("g/t") for gold, 0.94% for cobalt, 1.40% for bismuth and

0.71% for copper. The mineral reserve estimates were prepared by

Eugene Puritch, P.Eng., Fred H. Brown, P.Geo., and James L. Pearson,

P.Eng. of P&E, who are the Qualified Persons responsible for the 2012

FEED mineral reserves as defined by NI 43-101.Procon identified

additional high-grade mineral reserves outside of the open pit design

from the 2012 P&E mineral resources and have been included into a

combined mineral reserve statement. Henry Wulkan, P.Eng. Manager of

Projects for Procon is the Qualified Person responsible for the

additional underground mineral reserves as defined by NI-43-101.

Products and Markets:

NICO is a diversified specialty metals project with a countercyclical

gold co-product and by-product copper. The project will be well

positioned to be a reliable vertically integrated North American

source of supply of cobalt and bismuth products in a market where the

dominant producers are in counties where there is political

instability for cobalt (Congo - 60% of cobalt mine production) and

policy risks for bismuth and cobalt (China - 80% of bismuth mine

supply and 43% of cobalt refinery production). The location of the

SMPP in Saskatoon will benefit from its proximity to the North

American market and trade advantages from NAFTA as well as the

European Union. The plant will produce cobalt sulphate heptahydrate, a

chemical needed to manufacture lithium ion and nickel metal hydride

rechargeable batteries to take advantage of their growing use in

portable electronic devices and electric vehicles. The plant will also

produce 99.995% bismuth ingot and needles as well as bismuth oxide

with 89.7% bismuth content. Bismuth has traditional use in low

temperature and fusible alloys, pharmaceuticals and medicines such as

Pepto-Bismol @ as well as cosmetics. Bismuth demand growth is

primarily a result of its non-toxic properties which make it an

environmentally safe replacement of lead because of bans and

restricted use of lead in potable drinking water sources and

electronics (eg. from European Union - REACH program). Bismuth is

therefore being used in lead-free plumbing and electronic solders,

free-machining steel, brasses and aluminum, paint pigments and

automotive anti-corrosion coatings and windshield frits. Bismuth is

also one of the few metals, which expands when it cools and is

therefore used in products where dimensional stability is required

such as castings. The SMPP has been designed to produce multiple

value-added products that sell for significant premiums over metal.

The flexible design of the SMPP will also allow for simple

modifications to produce other cobalt and bismuth metals and chemicals

to take advantage of market opportunities and also to potentially

diversify into the recycling business.

Economic Analysis:

Fortune has evaluated the overall economics for the NICO project by

conventional discounted cash flow techniques, under the presumption

that the initial capital expenditure will be financed 30% by equity

and 70% by debt for a levered economic analysis contemplated in its

project financing discussions. All revenues and costs are expressed in

Canadian dollars, typically of fourth quarter 2013 value. Metal prices

denominated in US dollars have been converted to Canadian currency at

an exchange rate of C$1.00 = US$0.88. This exchange rate has been

assumed to remain constant throughout the life of the project.

The following table is a summary of the results of the base case

financial analysis. All production, revenue and cost data are

life-of-mine estimates.

NICO Economics

Item Units Value

Mine Life years 20

Open Pit Ore Mined thousand tonnes 32,500

Underground Ore Mined thousand tonnes 577

Concentrate Produced (dry) thousand tonnes 1,062

Gold Produced thousand troy ounces 814.4

Cobalt Produced (in sulphate) thousand pounds 69,526

Bismuth Produced thousand pounds 73,656

Copper Produced thousand pounds 11,195

Gross Revenue C$ million 3,842

Transport, Refining, Marketing C$ million 226

Net Smelter Return C$ million 3,596

Mine and Mill Operating Costs C$ million 746

Other Site Operating Costs C$ million 359

SMPP Operating Costs C$ million 599

Operating Profit C$ million 1,892

Corporate Administration, Interest, Fees C$ million 212

Royalties, Income Taxes C$ million 141

Cash Flow Before Capital Costs C$ million 1,540

Initial Capital Costs - NICO Project Site C$ million 347

Initial Capital Costs - SMPP C$ million 242

Sustaining and Working Capital C$ million 60

Reclamation Security Funding C$ million 53

Net Cash Flow C$ million 837

Pre-Tax Present Value (7%/year discount) C$ million 254

Post-Tax Present Value (7%/year discount) C$ million 224

Pre-Tax Internal Rate of Return %/y 15.6

Post-Tax Internal Rate of Return %/y 15.1

Base Case Price assumptions are US$ 1350/troy ounce for gold, US$16.00

cobalt/pound ("lb") (US$19.04 cobalt/pound in sulphate), US$10.50/lb

bismuth (US$12.64/lb bismuth in average production of combined ingot,

needles and oxide), and US$2.38/lb of copper at an exchange rate of

C$1 =US$0.88.

Sensitivity Analyses

Sensitivity analyses have been conducted to determine the effect on

NPV and IRR from application of variations in the base level prices

for the two principal co-products, gold and cobalt. The results are

summarized in the following table. These sensitivity analyses also

serve as a proxy for variations in ore grade, metallurgical recovery

or metal production, for either gold or cobalt.

Gold and Cobalt Price Sensitivity Analyses

Gold Price (US$/oz) 1,200 1,350 1,500

Pre-tax NPV, 7% (C$ million) 196 254 312

Pre-tax IRR ( 13.9 15.6 17.2

Post-tax NPV, 7% (C$ million) 168 224 281

Post-tax IRR ( 13.3 15.1 16.7

Cobalt Price (US$/lb) 13.00 16.00 19.00

Pre-tax NPV, 7% (C$ million) 124 254 383

Pre-tax IRR ( 11.4 15.6 19.4

Post-tax NPV, 7% (C$ million) 98 224 350

Post-tax IRR ( 10.7 15.1 19.0

A separate sensitivity analysis was also conducted, using the base

case production and cost estimates, but metal prices reflecting the

6-year price cycles for the metal that will be recovered from the

project to determine the impact of metal price cyclicity shown in

following table. Under this sensitivity analysis, the NICO Project

would be expected to yield an after-tax, undiscounted life-of-mine

cash flow of C$1.44 billion, levered pre-tax IRR of 23.6%, after-tax

IRR of 23.2%, levered 7% discounted pre-tax NPV of C$543 million and

after-tax 7% NPV of C$505 million.

Cycle Metal Prices Last Six Years

Metal Price Range

Low High

Gold (US$/oz) 1,200 1,900

Cobalt (US$/lb) 12.00 30.00

Bismuth (US$/lb) 7.00 19.00

Copper (US$/lb) 3.00 4.50

The capital costs for the NICO project were determined by the

engineering companies that were responsible for their respective

components of the study and totals $589 million for the first 2 years

of the project, including all direct and indirect costs and

contingencies. The underground mining fleet is assumed to be provided

by contracted service and the cost of the equipment is built into the

operating costs for the underground part of the mine. The open pit

mine fleet is planned to be sourced under a lease purchase from the

supplier and therefore only the deposit is included in project

capital, whereas most of the cost of this equipment is built into the

open pit mining costs. The total estimated pre-production capital

costs for the NICO project are summarized in the following table

expressed in constant Canadian dollars of fourth quarter, 2013 value.

The table does not include working capital, which is estimated at C$20

million.

Summary of Capital Costs

Location Pre-Production Capital (C$ million) Sustaining (C$ million) Total Capital (C$ million)

Direct Costs Indirect Costs Total

NWT 222.4 124.1 346.5 41.4 387.9

SMPP 165.0 77.5 242.5 16.4 258.9

Total 387.4 201.6 589.0 57.8 646.8

The following table shows the projected average annual metal

production for each of NICO's component commodities.

Average Metal Production

Average Metal Production

Gold (oz) Cobalt Bismuth Copper

(lbs) (tonnes) (lbs) (tonnes) (lbs) (tonnes)

Average Annual 41,360 3,560,426 1,615 3,856,830 1,749 582,494 264

LOM Total 814,394 69,525,678 31,536 73,656,311 33,410 11,194,663 5,078

Gross LOM Revenue C$ 1,249,354 1,489,240 1,047,393 29,912

% Revenue by Metal 33% 39% 27% 1%

The cash cost net of by-product credits for gold, cobalt and bismuth

were determined for the NICO project in the table below. Notably, the

cash costs per pound of cobalt and bismuth net of by-product credits

are low and demonstrate that NICO has very low operating costs for all

metals net of by-product credits. After capital has been repaid,

operations can be sustained during periods of low metal prices and

volatility.

Operating Cash Cost

Metal Price Case LOM Average Operating Cash Cost

Equivalent ounce of gold US$ 673.54

Ounce of gold, net of by-product credits US$ (702.12)

Equivalent pounds of cobalt US$ 9.50

Pound of cobalt, net of by-product credits US$ (5.19)

Pound of bismuth, net of by-product credits US$ (10.18)

The costs of operating the facilities at the NICO project and those at

the SMPP have been estimated separately. The total estimated

life-of-project ("LOP") operating costs are summarized in the

following table. The average annual costs shown in the table are based

on a project life of 20 years.

Estimated Life-of-Project Operating Costs

Location Life-of-Project Cost (C$ million) Average Annual Cost (C$ million) Average Unit Cost (C$/t ore milled)

NT 1,313.6 65.7 39.71

SMPP 599.1 30.0 18.11

Total 1,912.7 95.7 57.82

Summary of Operating Costs

The estimated LOM operating costs for the NICO project in the NT are

summarized in the following table. The average estimated cost is

C$39.71 per tonne of ore milled. These costs are expressed in constant

Canadian dollars of fourth quarter, 2013 value.

Summary of Project Site Operating Cost Estimates

Cost Centre Life-of-Mine Cost (C$ million) Average Annual Cost (C$ million) Average Unit Cost (C$/t total ore mined)

Open Pit Mining 271.2 13.6 8.20

Underground Mining 52.7 2.6 1.59

Processing (NWT) 422.4 21.1 12.77

Shared Services 355.2 17.8 10.74

Concentrate Transport 212.1 10.6 6.41

Total 1,313.6 65.7 39.71

The estimated LOM operating costs for the SMPP are estimated at C$599

million, or C$564 per tonne of bulk concentrate processed.

Average Cash cost per tonne of ore

Activity Unit Costs

Open Pit (per tonne of open pit waste and ore) C$2.08

Open Pit (per tonne of open pit ore) C$8.34

Underground Mining (per tonne of underground ore) C$ 91.40

Open Pit (per tonne of total ore) C$ 8.20

Underground (per tonne of total ore) C$ 1.59

Shared Services/Camp/G&A (per tonne of total ore) C$ 10.74

Processing and Concentrate Transport Costs (per tonne of total ore) C$ 37.30

Total (per tonne of total ore mined and processed) C$ 57.83

Mining:

NICO is planned to be mined primarily by open pit methods with

underground ores contributing 16% of the mill feed during the first

two years of operations. The open pit part of the mine will be a

conventional truck and shovel operation, accomplished in four phases

at an average waste to ore strip ratio of 3.0:1. The underground

portion of the mine will be mined by retreat blasthole open stoping

using a contractor and provides early access to gold-rich, higher

grade ores in the mine to optimize cash flow scheduling. Notably, most

of the underground pre-production development work for the underground

part of the mine has previously been constructed from the test mining

programs that were conducted in 2006 and 2007 by Procon at a total

cost of approximately C$20 million.

Processing:

The NICO ore will be processed in two stages at the NICO site and

SMPP, respectively. At the NICO site, 4,650 dry tonnes per day

(average) of ore will be processed in a crushing, grinding and

flotation concentrator to produce approximately 180 tonnes of wet bulk

concentrate per day. The high concentration ratio of NICO ores is a

significant economic attribute to the deposit, which allows the

Company to concentrate the valuable metals in 3.8% of the original ore

for efficient transport to southern Canada where significant process

cost savings can be achieved. The NICO bulk concentrate will be bagged

and transported by truck to Hay River, NT and transfer to rail for

delivery to the Company's proposed SMPP on the CN railway line near

Saskatoon.

At the SMPP, bulk concentrate will undergo additional grinding and

flotation to produce separate gold-bearing cobalt and bismuth

concentrates. The bismuth concentrate is treated by atmospheric acid

leach, followed by electro-winning to produce 99.5% bismuth cathode.

The cathode is then melted in a furnace and poured to make 99.995%

bismuth ingots or needles and with 60% of the production further

processed in an oxidation chamber to bismuth oxide with 89.7% bismuth

content.

The bismuth leach residue is fed into an autoclave together with the

cobalt concentrate for processing by pressure acid leach to dissolve

the metals. The solution that is produced will then be treated with

lime sequential neutralization to remove impurities and sodium

bicarbonate to precipitate cobalt carbonate. Copper is recovered from

the precipitate by re-leaching and Iron powder cementation to produce

90% metal cement precipitate. The cobalt circuit uses S-X (Cyanex

272), sequential stripping, solution evaporation & crystallization to

produce cobalt sulphate with 20.9% cobalt content.

Gold is recovered from the combined leach residue using cyanide and

precipitated by Merrill Crowe process followed by melting to pour gold

doré bars.

The process flow sheet, production of high value metal products and

metal recoveries have all been verified in three pilot plants as well

as laboratory scale test work that was carried out at SGS between 1997

and 2012. The decision to move the downstream processing of metals to

Saskatchewan was driven primarily by the availability of lower cost

power and the proactive support of the Government of Saskatchewan,

which has also passed attractive tax legislation to encourage

processing of raw materials that have been sourced from outside of the

province. The location near Saskatoon also provides access to rail, as

well as proximity to the highways, natural gas, lime and other

reagents, and a skilled labour pool of engineers and process plant

workers.

Fortune continues to work with Deloitte Corporate Finance Canada Inc.

to complete project financing agreements for the NICO project. The

Company has already announced a strategic investment by Procon

Resources Inc. in 2013 to provide interim financing to advance work on

the project, and negotiations are ongoing to secure final project

financing for the development. The Micon feasibility study will be

used to support ongoing negotiations with potential strategic partners

and their banks.

About Fortune Minerals

Fortune is a diversified resource company with several mineral

deposits and a number of exploration projects, all located in Canada.

The Company is focused on the development of the Arctos Anthracite

Project in British Columbia and the vertically integrated NICO

gold-cobalt-bismuth-copper project that is comprised of a mine and

mill in the NT that will produce a bulk concentrate for shipment to a

refinery for processing to high value metal products. In addition, the

Company owns the Sue-Dianne copper-silver-gold deposit and other

exploration projects in the NT. Fortune is focused on outstanding

performance and growth of shareholder value through assembly and

development of high quality mineral resource projects.

This press release contains forward-looking information. This

forward-looking information includes statements with respect to, among

other things, the proposed development of the NICO project and the

SMPP, the permitting process for the NICO project and the SMPP, the

anticipated production from the NICO project and the SMPP, the

anticipated capital and operating costs of the NICO project and the

SMPP and the anticipated economic returns therefrom. Forward-looking

information is based on the opinions and estimates of management as

well as certain assumptions at the date the information is given

(including, in respect of the forward-looking information contained in

this press release, assumptions regarding the Company's ability to

arrange necessary financing for the NICO project and the SMPP and

obtain all necessary permits for the NICO project and the SMPP and

assumptions regarding future metal prices, the capital and operating

costs of the NICO project and the SMPP and the production from the

NICO project and the SMPP). However, such forward-looking information

is subject to a variety of risks and uncertainties and other factors

that could cause actual events or results to differ materially from

those projected in the forward-looking information. These factors

include the inherent risks involved in the exploration and development

of mineral properties, the risk that the Company may not be able to

arrange the necessary financing to construct and operate the NICO mine

or the SMPP, uncertainties with respect to the receipt or timing of

required permits for the development of the NICO project or the SMPP,

the possibility of delays in the commencement of production from the

NICO project or construction of the SMPP, the risk of cost overruns,

the risk that future metal prices may be lower than anticipated and

other factors. Readers are cautioned to not place undue reliance on

forward-looking information because it is possible that predictions,

forecasts, projections and other forms of forward-looking information

will not be achieved by the Company. The forward-looking information

contained herein is made as of the date hereof and the Company assumes

no responsibility to update or revise it to reflect new events or

circumstances, except as required by law.

SOURCE Fortune Minerals Limited

-0- 04/02/2014

/CONTACT: Fortune Minerals Limited: Robin Goad, President, or Troy Nazarewicz,Investor Relations Manager, info@fortuneminerals.com, Tel.: (519) 858-8188, www.fortuneminerals.com; Renmark Financial Communications: Barbara Komorowski: bkomorowski@renmarkfinancial.com, or Farialle Pacha: fpacha@renmarkfinancial.com, Montreal Tel: (514) 939-3989, Toronto Tel. (416) 644-2020, www.renmarkfinancial.com

/Web Site: http://www.fortuneminerals.com

(OTC-QX:FTMDF /

OtherOTC:FTMDF /

Toronto:FT) /

CO: Fortune Minerals Limited

ST: Ontario

IN: MNG

PRN

-- TO96376 --

0000 04/02/2014 10:24:00 EDT http://www.prnewswire.com

Copyright © The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Most recent Business stories

Related topics

The Associated Press
    KSL.com Beyond Series
    KSL.com Beyond Business

    KSL Weather Forecast

    KSL Weather Forecast
    Play button