Construction begins on Lewiston paper mill upgrade


Save Story

Estimated read time: Less than a minute

This archived news story is available only for your personal, non-commercial use. Information in the story may be outdated or superseded by additional information. Reading or replaying the story in its archived form does not constitute a republication of the story.

LEWISTON, Idaho (AP) — Construction crews have begun work on a $160 million upgrade at a paper mill in Lewiston.

Workers poured a massive foundation for a new storage tank on Friday. The 8-foot-thick foundation will sit beneath a 110-foot-tall tank capable of holding 1,000 tons of high-density pulp.

The concrete was delivered by 10 trucks per hour for about 17 hours. It will take 56 days to cure.

Clearwater Paper spokesman Matt Van Vleet tells the Lewiston Tribune (http://bit.ly/1HNoMwv ) that the upgrade will make the pulp mill run more efficiently and will minimize downtime.

The plant employs 1,370 people.

___

Information from: Lewiston Tribune, http://www.lmtribune.com

Copyright © The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Most recent Business stories

Related topics

The Associated Press

    STAY IN THE KNOW

    Get informative articles and interesting stories delivered to your inbox weekly. Subscribe to the KSL.com Trending 5.
    By subscribing, you acknowledge and agree to KSL.com's Terms of Use and Privacy Policy.
    Newsletter Signup

    KSL Weather Forecast

    KSL Weather Forecast
    Play button