Willard Bay to be drained halfway to make room for repair


Save Story
KEY TAKEAWAYS
  • Willard Bay will be drained to 50% capacity for essential repairs.
  • Two corroded siphon pipes, installed in the 1970s, need urgent replacement.
  • Repair work starts Aug. 1, lasting six months, ensuring recreation continues.

WILLARD — Despite a plentiful snowpack, water levels at Willard Bay might look closer to what you'd expect after a few years of drought. Employees at Club Rec, a business that rents out water sports equipment, noticed the water dropping some weeks ago but didn't know why.

"It's dropping about two feet every week," manager Tyler Redington said. "I was honestly just kind of worried about the boats that we have and whether we're going to send out jet skis, but we're still doing it. We still have plenty of water."

Levels are expected to stop dropping once they reach about 50% of standard capacity, which Redington said will be enough to continue through the season — something he didn't know before.

The Weber Basin Water Conservancy District is lowering the levels to make way for a much-needed repair. CEO and General Manager Scott Paxman said that two siphon pipes on the north end of the dike are corroding away. They were installed in the 1970's.

"Those siphons help feed several of the users out there: compass minerals, as well as the bird refuge," Paxman said. "They've been corroding from the inside and the outside. We've repaired them several times. The last time we repaired them was, I think, 2017."

That last repair was supposed to buy the conservancy district about another five years of life. However, Paxman said increased contractor prices after COVID-19 made it difficult to move forward, as bids came in at three times what they had budgeted for the job. Now that prices have come back down, he said they can move forward, but the repair now is more urgent.

"Either way, we had to get it done and we had a limited time to do it in as well," Paxman explained. "We also couldn't do construction during the winter months because of the freeze-thaw issues with the backfill that we have to put back into the dike."

Levels at the reservoir will be maintained at around 50% while the work moves forward, starting around Aug. 1 and is expected to take about six months to complete. The siphon pipes will be replaced with a direct outlet system, which Paxman said should require less maintenance. He adds that there should be plenty of water remaining for recreation and to keep the boat ramps open.

The Key Takeaways for this article were generated with the assistance of large language models and reviewed by our editorial team. The article, itself, is solely human-written.

Most recent Outdoors stories

Related topics

Mike Anderson, KSL-TVMike Anderson
Mike Anderson often doubles as his own photographer, shooting and editing most of his stories. He came to KSL in April 2011 after working for several years at various broadcast news outlets.
KSL.com Beyond Series
KSL.com Beyond Business

KSL Weather Forecast

KSL Weather Forecast
Play button